Our clients in Carrigaline required a full balcony strip-out and preparation works ahead of a planned re-roofing project.
The goal was to safely remove existing balcony finishes and damaged materials, prepare the structure for upcoming roofing works, and ensure the area was ready for a smooth and efficient refurbishment process.
Installed scaffolding around the balcony to provide a safe and stable working platform.
Included guardrails and proper access points in accordance with safety regulations.
Carefully removed the existing balcony railings to gain full access to the work area.
Stripped back the balcony surface, removing all damaged and rotten timber.
Removed deteriorated rubber sealant to expose the base structure.
All waste materials and debris were safely removed from the site.
Work area was cleaned and cleared to ensure a safe and efficient handover.
Site was left fully prepared for the carpenter to proceed with the installation of a new roof structure.
Scaffolding access was retained for the next phase of works.
The completed project provided a clean and fully prepared balcony structure ready for the next phase of re-roofing works. Existing damaged materials and outdated finishes were safely removed, allowing clear access for contractors and ensuring the structural areas could be properly inspected and refurbished.
The strip-out and preparation works helped streamline the overall renovation process while improving site safety and setting the foundation for a durable, weather-protected roofing system.